The corner of Highland Avenue and First Avenue has been empty since 2019. In mid-October it got a name, a design team and a projected opening year. About a quarter mile away, the 629 Highland Avenue lot won Planning Board approval almost three years ago and is still a fenced excavation. In Needham right now, an approval is a weaker sign that something will open than the cost of building it.
Here is where the sites along this stretch stood heading into the end of October 2026.
| Site | What's planned | Approval status | Latest reported status |
|---|---|---|---|
| 1 First Ave., former Acapulcos | Two restaurants, two retailers, 8,500 sq. ft. | Construction documents still headed to town review | Projected to open in 2027 |
| 629–661 Highland Ave. | 50,000 sq. ft. medical office building | Approved December 2023 | As of July 2026, a hole in the ground with the owner weighing other uses |
| 557 Highland Ave., former Muzi | Senior-oriented mixed use | Needs a zoning change | Town Meeting vote estimated for May or fall 2027 |
| 40 Franklin St., former You-Do-It | Onyx Partners offices, Pure Hockey on the ground floor | Business signs approved July 27, 2026 | Renovation was nearing completion as of July |
A corner with a long restaurant history
The Needham Observer reported on October 14 that the former Acapulcos site will become One First at Needham Crossing. It is an 8,500-square-foot project owned by James McManus of Fox and Hound Properties of Holliston and developed with Feldman Development Partners of Boston. The Boston design studio SPARC is handling the design. The planned lineup is a restaurant with a patio, a fast-casual spot, a boutique shop and a technology retailer. No tenants have been finalized. The next step is construction documents for the town's review and approval process, and the project is projected to open in 2027.
The corner has been a restaurant site for decades. A Howard Johnson's came first, then a Ground Round, and Acapulcos took over in 2009 before closing in 2019. Demolition of the old building was finished in June 2026.
The years in between saw at least one much bigger idea. In December 2019, the development group behind the site talked with the Planning Board about pairing a retail bank with an iFLY indoor skydiving facility. According to MetroWest Daily News coverage at the time, the concept called for a 65-foot iFLY building. Board members raised questions about use and parking, and no permit applications had been filed. By this summer the skydiving idea was off the table.
Going from a 65-foot entertainment building to a single-story mix of restaurants and shops is a step down in scale. That smaller scale is exactly what the rest of the corridor suggests gets built.
The lot that won approval and stayed a hole
Head south on Highland Avenue to the block between Cross Street and Arbor Road. Five 1960s commercial buildings came down there in the summer of 2025 to make room for a two-story, 50,000-square-foot medical office building. The site once held Kennedy Brothers physical therapy, Med-Equip Healthcare Supply, HIY Pilates and the nonprofit Hope and Comfort. Boston Development Group, the Newton-based owner, got Planning Board approval in December 2023.
Approval was never the problem. Speaking to the Needham Observer in August 2025, president and CEO Jodie Zussman laid out the math. The town's zoning bylaw requires five parking spaces for every 1,000 square feet of office space. Another bylaw caps buildings at 40 feet. Together, the two rules work out as follows:
- A 50,000-square-foot building at five spaces per 1,000 square feet needs 250 parking spaces.
- The 40-foot height limit means much of that parking has to go underground.
- Underground parking takes up most of the project's cost.
"At this point, everything that we've looked at is really just a break even and almost a little bit of a loss."
That was in 2025. Zussman also said then that the firm would not build until the numbers worked and a tenant was signed. In the Observer's July 2026 update, she said the company had "not been able to get to the finish line" because of construction costs and was talking with developers about other uses. The Observer noted that a different use could bring zoning challenges of its own. No newer proposal had been filed for the site by mid-October.
Why the smaller plan moved first
On paper, One First is 8,500 square feet and 629 Highland is 50,000. That makes the corner project less than a fifth the size of the office building that stalled. It also skips the use that brought the 250-space requirement at 629 Highland. The owner there pinned most of the cost on parking tied to office square footage. One First is restaurants and shops at a smaller scale, and its own costs and requirements still have to go through town review.
The two lots also show different meanings of "progress." At 629 Highland the paperwork is done and the money isn't there. At One First the paperwork hasn't started, but an owner, a co-developer, an architect and a target year have all been announced. SPARC's Aksel Solberg told the Observer the design work dates back to 2021, and that the site's "challenging geometry" made it hard to fit buildings, street frontage and car circulation onto the lot. Five years of design refinement before a filing is a long time. But a plan reworked that long before going to the town is more likely to make sense once it gets there.
The former Muzi site needs a vote before construction can start
The former Muzi site at 557 Highland Avenue is the largest open question on the corridor, and it is further from construction than either lot above. At an April 7 Planning Board preview, The Bulfinch Companies showed a concept with up to 480 homes, as much as 100,000 square feet of medical office space and 10,000 square feet of retail, as the Needham Observer reported.
By July the concept had shifted. Planning Director Lee Newman told the Planning Board that Bulfinch was "advancing the idea of doing a continuing-care facility comparable to North Hill at that property." Bulfinch had aimed to put a new zoning framework on this fall's Town Meeting warrant, and that hadn't happened. Newman expected an informal presentation to the board in early fall and put the likely Town Meeting zoning vote at May 2027 or fall 2027. The Planning Board's October 6 agenda didn't include a Muzi item. The Observer also reported that Bulfinch may need a development partner with housing experience.
This site follows the same pattern as the others. The April concept leaned heavily on medical office space, the same use that ran into cost trouble a quarter mile down the road. The July direction was a different product altogether.
The building that kept its walls
The site closest to opening skipped the empty-lot phase entirely. At 40 Franklin Street, Onyx Partners renovated the former You-Do-It Electronics Center instead of tearing it down. In July, the Observer reported the rebuild was nearing completion. Onyx planned to take the top two floors, and Pure Hockey planned to move into the ground floor from its Highland Avenue location. On July 27, the Design Review Board approved the business signs for Onyx and Pure Hockey, with placement conditions.
The rooftop You-Do-It sign is on its own track. Current bylaws no longer allow rooftop signs, and the sign would have lost its grandfathered status once the renovation happened. The Needham Historical Commission voted on June 15 to add it to the town's historic inventory, which is the first step toward keeping it. The July 27 Design Review Board decision didn't cover the rooftop sign, and the minutes noted that a state approval was still pending. Doug Richardson of Onyx told the Observer the company sees the sign as "no different than the Citgo sign in Kenmore Square."
40 Franklin needed no new underground garage, no zoning change and no new tenant search for a vacant lot. It reused an existing structure for an office firm and a local retailer, and its approvals so far have been about signs. Of the four sites, it is the one that moved quickest.
What sets the pace from here
Two dates are clear. One First is aiming for 2027, after its construction documents clear town review. The Muzi zoning question is headed to Town Meeting in May or fall 2027 at the earliest. 629 Highland has no date at all. Its next step depends on whether a different use can work under the same parking and height rules that stopped the first one. For the latest on any of these sites, check the Planning Board's archive of submitted applications on the Town of Needham site. Highland Avenue is changing in a different way than Great Plain Avenue, where new leases were signed before the street design was settled. More of Needham's ongoing coverage is on our Needham neighborhood page.
If you own a home or commercial property near the Highland Avenue corridor and want to know how these projects might affect its value, Edward Gaeta follows these sites closely and can walk you through it. Get your free market valuation or a 24-hour cash offer, whichever fits your timeline.